Lot SS1.1 in experimental section for deep drainage and storage pipeline system engineering of Suzhou River

Business sector: Water conservancy and water utilities
Location: Shanghai
Commencement time: January, 2018
Participation mode: Engineering procurement construction
Shield tunneling machine specifications: Slurry balance shield tunneling machine with a diameter of 11.73m
Project breakthroughs: Super-deep diaphragm (103 m) and ultra-deep foundation pit (56.6 m)

Copyright©隧道股份. All rights reserved.

中文English